The redevelopment of the Felling shops has been a long time coming.
The original plan was
The original plan was
Planning application – 20th January 2012
Planning approval – March 2012
Start on site – August 2013 (revised date)
Completion – May 2014
The actual start on site was Nov/Dec 2014
Council building getting nibbled
Co-op store, Bamling shop and Council Offices gone
photo courtesy of Michael
Rubble cleared 18 Dec '14
Another one from Michael..19th Jan 1015
Steel work going up 13th March 2015
14th March 2016
In the first hour of opening 14th March 2016